All Projects Page

Filter Category (field_filter_category)
  • Rajasthan 1 is a 5 MW project that was constructed over a period of nine months. The project was commissioned in December 2011. The PPA was signed in January 2011 with NTPC Vidyut Vyapar Nigam Limited with a tariff of Rs. 11.94 per kilowatt-hour for a period of 25 years.

    2011
    Project recognized by MNRE for early commissioning under JNNSM Phase-1 Batch-1
    NTPC Vidyut Vyapar Nigam Limited
    Solar Power Projects
    Nagaur, Rajasthan
    5 MW
  • Punjab 1 is a 2 MW project that was commissioned in 2009. The offtaker for the project is NTPC Vidyut Vyapar Nigam Limited, with a tariff of Rs. 17.91 per kilowatt hour for a period of 25 years. This was also the first private utility scale solar project built in India, making us the longest tenured private solar power generating company in India.

    2009
    India's first private utility scale solar project
    NTPC Vidyut Vyapar Nigam Limited
    Awan, Punjab
    2 MW
  • Rajasthan 4 is a 5 MW project that commenced operations in November 2015. The PPA for the was signed with Solar Energy Corporation of India in February 2015 with a tariff of Rs. 5.45 per kilowatt hour with VGF for 25 years.

    2015
    First private project under JNNSM that provides electricity to Indo-Pak border outposts
    Solar Energy Corporation of India
    Solar Power Projects
    Jaisalmer, Rajasthan
    5 MW